12
3.
Remove the plastic caps from all mounting
bolts on the concrete installation pad.
4.
Use a wire brush to clean out threads if any
concrete is on the upper bolts.
5.
Place a leveling nut and washer
on each of the four corner
bolts.
6.
Leave approximately 6.4 mm
(1/4 in) between the bottom of
the leveling nuts and the
concrete. Check nut positions
relative to each other with a
level.
7.
Retrieve the lifting straps from either the toolkit or the main crate. If there is no separate toolkit:
rest the crate in a stable position and unlatch the lid. Retrieve the lifting straps just inside and
securely re-fasten the lid.
8.
Transport the crate close to the installation site. If using a forklift, position the forks at least
762 mm (30 in) apart to assist with stability.
WARNING:
THE CRATE IS HEAVY AND CAN CAUSE INJURY OR
DEATH IF DROPPED. DO NOT STAND OR MOVE BENEATH THE
CRATE AS IT IS BEING TILTED. TAKE PRECAUTIONS AGAINST THE
CRATE TIPPING OR SLIDING.
6.4 mm (1/4 in)
250_IGcombo.pdf 18
11/18/2019 3:37:40 PM