![KSB Hya-Solo DV Series Скачать руководство пользователя страница 28](http://html1.mh-extra.com/html/ksb/hya-solo-dv-series/hya-solo-dv-series_installation-and-operating-manual_2006480028.webp)
Operations
Done
12
Record all system conditions that do not correspond to our specifications or to the purchase
order in the commissioning report (i.e. no dry running protection or inlet pr max.
pressure of pressure booster system higher than 16 bar).
13
Complete the commissioning report together with the operator/user and instruct the operator/
user as to the function of the system.
7.4
Shutdown
NOTE
As long as the pressure booster system is out of operation, water is supplied directly at
p
inl
through the pressure booster system.
Set master switch to "0".
NOTE
Drain the pressure booster system for prolonged shutdown.
7 Commissioning/Start-up/Shutdown
28 of 56
Hya®-Solo DV