![KSB Hya-Solo DV Series Скачать руководство пользователя страница 21](http://html1.mh-extra.com/html/ksb/hya-solo-dv-series/hya-solo-dv-series_installation-and-operating-manual_2006480021.webp)
6
Installation at Site
6.1
Installation to DIN 1988
Install pressure booster systems either in the technical equipment room or in a well-
ventilated, frost-free, lockable room used for no other purpose. No harmful gases are
allowed to enter the place of installation. An adequately sized floor drain (leading to
a sewer or equivalent) must be provided.
The system is designed for a maximum ambient temperature of 0 °C to +40 °C at a
relative humidity of 50 %.
NOTE
Do not install pressure booster systems next to sleeping or living quarters.
If expansion joints (KSB accessory) are used for damping vibrations, their fatigue
strength (endurance limit) must be given due consideration. Expansion joints must be
installed to allow quick and easy replacement.
6.2
Checks to be carried out prior to installation
Place of installation
WARNING
Installation on foundations which are unsecured and cannot support the load
Personal injury and damage to property!
▷
Make sure the concrete of the installation surface is of sufficient strength (min.
X0 to EN 206-1).
▷
Place the pressure booster system on firmly set concrete only.
▷
Place the pressure booster system on level surfaces only.
▷
Refer to any weights given.
NOTE
The anti-vibration mounts of the pressure booster system provide adequate insulation
against solid-borne noise.
Check structural requirements.
All structural work required must have been prepared in accordance with the
dimensions stated in the outline drawings.
6.3
Installing the pressure booster system
WARNING
Top-heavy pressure booster systems
Risk of personal injury in case of pressure booster systems equipped with small pumps!
▷
Pressure booster systems awaiting final installation must be secured against
tipping over.
▷
Firmly anchor the pressure booster system to its foundation.
Remove packaging before installing the pressure booster system. Connect the
pressure booster system's inlet line and discharge line to the corresponding site
distribution lines.
NOTE
In order to avoid transmission of piping forces onto the pressure booster system and
transmission of solid-borne noise, we recommend to install length-limited expansion
joints.
6 Installation at Site
Hya®-Solo DV