The following work must be completed in accordance with
installation instructions:
Pre-start up
A. General
1.
All major components, boxes, and crates have been received and accounted for
by a YORK/Johnson Controls Service representative.
2.
Any damage, or signs of possible damage, have been documented to the
transportation company.
3.
Unit is installed in an area protected from weather and maintained at a
temperature above freezing.
4.
Vibration-proof rubber sheets are installed between chiller base and site
foundation.
5.
Unit is located in accordance with minimum clearance dimensions, foundation
bolts are properly installed, and the levelness of the unit is within acceptable
range. (Tolerance for leveling length is 0.039 in. for every 39 in. and width is 0.039
in. for every 39 in. (length: 1.0 for every 1,000 mm and width:
1
.0 for ever
y
1,000
mm)).
6.
HG compound gauge pressure reading is about the same as before shipment.
7.
Thermal insulation is done according to the specifications detailed in this
manual.
8.
Valves, thermowells, plugs, and sight glasses are not covered with insulation.
B. Piping
1. Piping is installed between the unit at the source of supply.
2. The following and its related equipment are ready for operation:
a. Chilled or hot water pump
b. Cooling water pump
c. Cooling tower fan
d. Residential hot water pump
3. Detachable flanges are properly installed close to the:
a. Chilled or hot water box
b. Cooling water box
c. Residential hot water box
4. A mesh strainer is installed on the:
YHAU-CGN/H-CXR(M) Small Direct Fired Absorption Chiller-Heater Checklist
2
Model YHAU-CGN/H-CXR(M)Double Effect Direct Fired Small Absorption Chiller-Heater