Assembling Tees to Mounted Filter Assembly
Following the PVC Gluing Guidelines in
Section E
, prime and glue the
Before Filter Tee Assembly
from
Step 2
to the IN side of the
Filter Cap Assembly
and
the
After Filter Tee Assembly
from
Step 3
to the OUT side of the
Filter Cap Assembly
as shown below.
Assembling Gauges to Tees
Following the PVC Gluing Guidelines in
Section E
, prime and glue one of the
Pressure Gauge Assemblies
from
Step 5
to the
Before Filter Tee Assembly
and
the other
Pressure Gauge Assembly
from
Step 5
to the
After Filter Tee Assembly
as shown below.
Install pressure gauge so
it can be easily viewed.
Install pressure gauge so
it can be easily viewed.
Pressure
Gauge
Assembly
Pressure
Gauge
Assembly
Prime & Glue
Prime & Glue
Tee must
point up
Tee must
point up
Prime & Glue
Prime & Glue
After Filter
Tee Assembly
Before Filter
Tee Assembly
Filter Cap Assembly
11
12
IS275-17L
J&D Manufacturing • 6200 Hwy 12 • Eau Claire, WI 54701 • 1-800-998-2398 • www.jdmfg.com
Section F - Page 5/6
Section F
Filter System Assembly & Installation
Section F
Assembling Check & Ball Valve to Mounted Filter Assembly
Following the PVC Gluing Guidelines in
Section E
,
prime and glue the
Check & Ball Valve Assembly
from
Step 4
to the
Before Filter Tee Assembly
as shown
below.
Install ball valve with the lever away from the
wall so lever can be turned without interference.
Prime & Glue
Check & Ball Valve Assembly
13