BreakingPoint 20 Installation Guide
31
BreakingPoint Systems Inc. © 2005-2015
• Ensuring that the operating environment is 15°C to 35°C (59°F to 95°F)
Required Tools and Mounting Steps
In order to mount the BreakingPoint 20 chassis, you will need the following tools:
• Phillips screwdriver
Use the following instructions to mount the BreakingPoint 20 chassis to the 19-inch equipment
rack from the front. This process requires at least three people.
To install the BreakingPoint 20 to a 19-inch equipment rack:
1. Using two people, one on each side of the chassis, lift the chassis.
Note:
With one hand, hold the bottom of the chassis, with the other, hold the back of the chassis
for complete support of the system.
2. Raise the chassis to the desired height in the equipment rack.
Note:
The chassis should be placed at least 3 feet above the ground to prevent dust particles
from collecting inside the chassis.
3. Insert the chassis between the rack rails.
4. Align the four mounting holes on the chassis to the four mounting holes on the equipment rack.
5. Secure the unit using the 10-32 x .75 supplied rack screws through the holes on the chassis and
into the mounting rails on the equipment rack.
Note:
This step must be done by the third person, while the two other people are holding the
chassis.
Installing the Blade
BreakingPoint recommends that you install the first blade into the bottommost slot of the chassis. If
only one blade is installed in the chassis, it must be installed in the bottommost slot.
To install the blade:
1. Locate the card guide rails.
2. Place the blade onto the card guide rails.
3. Slide the card slowly into the slot until the front panel of the blade is about 1 inch from the
chassis.
Note:
You may experience some resistance when you slide the blade into place; however, this
is normal behavior.
4. Verify that the ejectors and thumb fasteners are aligned with the inner mounting rails on the
BreakingPoint 20.
5. Push the blade into place once you have verified that the ejectors and thumb fasteners are
properly aligned.
Содержание BreakingPoint 20
Страница 1: ...BreakingPoint 20 Installation Guide Release 3 4 Jan 2015...
Страница 4: ...4 BreakingPoint 20 Installation Guide Release 3 4...
Страница 11: ...Documentation Feedback BreakingPoint BreakingPoint 20 Installation Guide iv BreakingPoint Systems Inc 2005 2015...
Страница 45: ...BreakingPoint 20 Installation Guide 34 BreakingPoint Systems Inc 2005 2015...
Страница 55: ...Update Questions BreakingPoint 20 Installation Guide 44 BreakingPoint Systems Inc 2005 2015...
Страница 61: ...CLI Commands BreakingPoint 20 Installation Guide VI BreakingPoint Systems Inc 2005 2015...