Testing the System
25
Testing the Hardwire Input
Module (HIM)
To test the optional Hardwire Input Module:
1. Verify that all wiring at the panel and the HIM
are correct.
2. Turn on the panel power switch.
Note
If the red HIM LED is not flashing continuously, set the panel
PROGRAM/RUN switch to RUN and turn off the panel pow-
er switch. Verify that all wiring is correct and that all bus de-
vices (including hardwire touchpads) are set with different
unit ID numbers.
Whenever the HIM unit ID number is changed, you must
turn off the panel power switch, turn it back on, and then en-
ter the program mode for the panel and HIM to communi-
cate successfully.
If the system uses hardwire sensors only, turn off upper
sensor 94 (Receiver Failure) in the panel.
3. Set the panel’s PROGRAM/RUN switch to
PROGRAM.
If the alphanumeric display continues to read 1-
OFF and the 1 is flashing, you must enter the in-
stall code (four digit install access code) to get the
panel into the program mode.
The alphanumeric display should read PRO-
GRAM MODE and the red HIM LED should be
flashing continuously, indicating successful bus
communication with the panel.
4. Set the panel’s PROGRAM/RUN switch to RUN
and refer to the “Testing Sensors” section for
testing hardwired sensors connected to the HIM.
Testing the Hardwire Output
Module (HOM)
To test the optional Hardwire Output Module:
1. Verify that all wiring at the panel and the HOM is
correct.
2. Turn on the panel power switch.
3. Set the panel’s PROGRAM/RUN switch to
PROGRAM.
If the alphanumeric display continues to read 1-
OFF and the 1 is flashing, you must enter the in-
stall code (four digit install access code) to get the
panel into the program mode.
The alphanumeric display should read PRO-
GRAM MODE and the red HOM LED should be
flashing continuously, indicating successful bus
communication with the panel.
4. Set the panel’s PROGRAM/RUN switch to
RUN.
5. Activate each of the programmed system trigger-
ing events to verify correct HOM output
response.
Note
If the red HOM LED is not flashing continuously, set the
panel PROGRAM/RUN switch to RUN and turn off the pan-
el power switch. Verify that all wiring is correct and that all
bus devices (including hardwire touchpads) are set with dif-
ferent unit ID numbers.
Whenever the HOM unit ID number is changed, you must
turn off the panel power switch, turn it back on, and then en-
ter the program mode for the panel and HOM to communi-
cate successfully.
Testing the X-10 Lamp
Modules
Refer to table C.4 in appendix C for X-10 lamp and
appliance module control operation.
To test the X-10 Lamp Modules:
1. Press COMMAND + 0 repeatedly to turn all
lights on and off together. Appliance modules, if
any, are all turned off by pressing COMMAND
+ 0 but are not all turned on this way.
2. Press BYPASS + 1 repeatedly to turn light 1 on
and off.
3. Repeat step 2 for remaining assigned lamp and
appliance module unit numbers.
4. Press ACCESS CODE + 3 to arm the system to
Level 3-Away. Unit 1 light should turn on and
stay on for 5 minutes. Unit 2 light should blink
three times to indicate the arming level. All
remaining lights should be unaffected.
5. Press ACCESS CODE + 1 to disarm the system.
If Unit 1 light was on for an entry or alarm, it