verify the correct functioning of the system of the outlet condense, also in the external parts of the
boilers, i.e. the eventual condense collector installed on the flue outlet: verify that the liquid flow is
not obstructed and that there are not inlets of gaseous combustion products inside the system itself;
f
verify that the conditions for the air inlet are granted, in case of a boiler placed inside a piece of
furniture;
f
when prescribed, or if it is necessary (i.e. if you find exces-
sive residual in the combustion group or in the funnel of the
condense), verify that the combustion is correctly regulated:
go on in this chapter as described in the paragraph "Com
-
bustion test and adjustment" on page 31;
f
verify the correct functioning of the boiler in heating and do-
mestic hot water version;
f
fill in the foreseen documentation and leave to the user the
copy of his competence.
Access to the inside of the boiler
1. Unscrew the screws
1
and remove the lower grid
2
, if
any;
Remark: Lower grid is spare inside packing, not assem
-
bled.
2. Push the front panel
3
upwards and remove it, unhook
-
ing it from the heads of the screws
4
;
3. unscrew the two screws
7
and overturn downwards the
control panel
8
;
4.
Should the removal of the side panel(s)
9
be necassary:
•
unscrew the screws
5
and remove the brackets
6
;
•
remove the panel
9
upwards, slightly displacing it out
-
wards to free it from the chassis, unhooking it from
the tongues
10
;
5.
after the regulations (described in the following para-
graphs), close the boiler repeating everything in the oth-
er sense, carefully hooking (if removed) the panel(s)
9
to the tongues
10
and the front panel
3
to the screws