SECTION II
Installation
Page 2.2
BP+10-150
12/95
2.2 Mechanical Preparation of UPS
(continued)
1.
Insure that all packing, both external and internal, has been
removed from the UPS.
2.
Open right-hand front door of the UPS.
3.
For standard bottom cable entry, unscrew screws holding the panel
around the circuit breakers and remove the panel. Then, remove the cable access
panel on the bottom of the UPS by removing six (6) screws.
4.
For optional top cable entry, remove the right side cover by removing
two (2) screws at the bottom (inside front and back) and lift the cover. Drill holes in
the appropriate conduit plate of suitable size for the cables to be inserted through
it, and replace the plate.
5.
Fasten leveling feet (packed inside) to the four bottom corners of the
UPS cabinet. Access to the inside of the cabinet is not required. Refer to Figure 2-1.
(An optional pedestal mount may replace leveling feet and casters.)
a.
First screw the leveling foot screw through the leveling plate.
b.
Use two sets of 114-20 x 1” screw, flat washer and lock washer to
fasten the leveling plate to the bottom of the cabinet. Two threaded holes are in the
floor of the cabinet to receive them.
c.
Screw in each leveling foot until it is a minimum of 0.75 in (1.9 cm)
above the floor level. Tighten locking nut to keep it there.
6.
If an IPM battery pack is to be attached to the left side of the
UPS,
perform this sequence. If the battery cabinet is not to be attached to the left
side of the UPS, skip Step 6.
a.
Open the left-hand front door of the UPS. Remove eight (8) screws
from the lower metal cover to remove the cover. When the three-(3) upper screws
are removed, the clear plastic guard above will also come off.