UPS5000-S-600 kVA
User Manual (Three-phase, Three-wire)
3 Installation
Issue 05 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
74
Step 2
Pull the cable to the copper bar to which the cable is to be connected, determine the cable
length, and mark the cable at the position where the cable is to be cut.
Step 3
Pull the marked cable out of the cabinet, cut the cable from the marked position, strip the
cable, and crimp a terminal.
Figure 3-29
Preparing a cable terminal outside the cabinet
Choose an appropriate cabling route based on the actual situation. The figure is for reference only.
Step 4
Connect the cable with a crimped terminal to the corresponding copper bar.
Step 5
Clean foreign matter inside the cabinet.
----End
3.2.5 Routing Cables
Context
This section introduces the dual mains scenario. If single mains is used, you do not need to
remove the copper bars between the mains and bypass input terminals or connect the bypass
input cable.
Procedure
Step 1
Open the front door of the bypass cabinet and remove the covers of the power distribution
subrack.