UPS5000-S-600 kVA
User Manual (Three-phase, Three-wire)
3 Installation
Issue 05 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
63
Step 5
Adjust the cabinet to ensure that the expansion bolt holes align with the half holes below.
Step 6
Use expansion bolts to firmly lock the front and rear antiseismic kits to the ground.
Figure 3-13
Locking the antiseismic kits to the ground
Step 7
Reinstall the support baffle plates and rear covers in the cabinet.
Step 8
Install the front, rear, left, and right anchor baffle plates.
----End
3.2.3.2 Installing an IP21 Component
Procedure
Step 1
Install leveling feet at the bottom of the IP21 component, with two long feet on the front and
two short feet at the rear.
Refer to the "front" and "back" silk screens on the surface of the IP21 component.
Select the mounting holes for leveling feet based on the cabinet width onsite.
Figure 3-14
Installing leveling feet
Step 2
Secure the IP21 component to the top of each cabinet using four M12 screws.