shows the cable connections for an NO EPO switch.
Figure 3-47
Cable connection for an NC EPO switch
Figure 3-48
Cable connection for an NO EPO switch
When the EPO switch is in the NC state, remove the jumper between EPO_NC and EPO_12V
before connection. When the EPO switch is turned off, EPO is triggered.
When the EPO switch is in the NO state, ensure that the jumper is connected between EPO_NC and
EPO_12V. When the EPO switch is turned on, EPO is triggered.
3.2.5 Connecting Communications Cables
Procedure
Step 1
Connect the external network management device to the RS485 port.
Step 2
Connect the network port on a PC to the FE port.
----End
3.2.6 (Optional) Installing a Battery Cabinet
Procedure
Step 1
A battery cabinet is installed in the way as the UPS cabinet.
Step 2
Use connecting kits to connect the UPS cabinet and battery cabinet.