UPS5000-E-(25 kVA-75 kVA)-BF
User Manual
3 Installation
Issue 07 (2019-12-13)
Copyright © Huawei Technologies Co., Ltd.
78
Step 8
The signal cables are routed in and out from the bottom and the top. Route the left signal
cables along the left side of the cabinet and the right signal cables along the right side of the
cabinet, and then bind the cables to the cabinet, as shown in
Figure 3-45
Routing signal cables from the bottom of the cabinet
The number and color of signal cable in the figure is for reference only.