3 Power-On Commissioning
Issue 01 (2014-3-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
28
The fire extinguishing system meets requirements if operations during the commissioning
have expected results and corresponding alarms are generated in the iManager NetEco
management system.
The system can be put into use if operations during the commissioning have expected
results.
To ensure the normal operation of the fire extinguishing system, the dowel tightening the
fire cylinder solenoid valve and the container valve must be removed.
the dowel.
Figure 3-22
Dowel tightening the fire cylinder solenoid valve
----End