4.5. Electrical
WARNING
– All electrical wiring MUST conform to local codes, regulations, and the National
Electric Code (NEC).
WARNING
– Ground and bond pump before connecting to electrical power supply. Failure to
ground and bond pump can cause serious or fatal electrical shock hazard. Do NOT ground to a gas
supply line. To avoid dangerous or fatal electrical shock, turn OFF power to pump before working on
electrical connections. Fire Hazard - match supply voltage to pump nameplate voltage. Insure that the
electrical supply available agrees with the pump’s voltage, phase, and cycle, and that the wire size is
adequate for the amps rating and distance from the power source. Use copper conductors only.
4.6. Electrical Specs
1.
Voltage: 230VAC, 60Hz, Single Phase
2.
Amps: 10.9
3.
Speed Range: 600-3450 rpm
Use copper conductors only. For indoor & outdoor use, connect the pump to a 15 amp branch circuit in
accordance with local codes, regulations, and the National Electric Code (NEC). A disconnecting
means located at least 5 ft. from the inside wall of the water vessel must be provided.
4.7. Voltage
Voltage at pump MUST NOT be more than 10% above or below nameplate rated voltage, or
components may overheat, causing overload tripping and reduced component life. If voltage is less than
90% (207 VAC) or more than 110% (253 VAC) of rated voltage (203) when pump is running at full
load, consult the power company.
4.8. Grounding and Bonding
1.
Install, ground, bond, and wire pump in accordance with local or national electrical code
requirements.
2.
Permanently ground pump. Use green ground terminal provided under access plate; use size and
type wire required by code. Connect ground terminal to electrical service ground.
3.
Bond pump to water structure. Bonding will connect all metal parts within and around the water
structure with a continuous wire. Bonding reduces the risk of a current passing between bonded
metal objects, which could potentially cause electrical shock if grounded or shorted. Reference NEC
codes for all wiring standards including, but not limited to, grounding, bonding and general wiring
procedures.
4.
Use a solid copper conductor, size 8 or larger. Run wire from external bonding lug to reinforcing
rod or mesh. Connect a No. 8 AWG (8.4 mm
2
) [No. 6 AWG (13.3 mm
2
) for Canada] solid copper
bonding wire to the pressure wire connector provided on the motor housing and to all metal parts of
the water structure and to all electrical equipment, metal piping (except gas piping), and conduit
within 5 ft. (1.5 m) of inside walls of the water structure.
USE ONLY HAYWARD GENUINE REPLACEMENT PARTS
_____________________________________________________________________________________
Hayward Flow Control
www.haywardflowcontrol.com
1-888-HAY-INDL (1-888-429-4635)
IS3401VSPFC Rev A 12/08/14
Pg. 9 of 36