Section 2:
Installation
Copyright © 2011 Haskris Company
8
www.haskris.com
Version R1600-X-R407C-XXX Instruction Manual Rev00
Termination point
on electrical block
PLEASE NOTE: The 1½” pilot hole is for electrical power pass-through
only. DO NOT TERMINATE CONDUIT OR USE CONDUIT
CONNECTORS AT THE ELECTRICAL BRACKET.
Main power will terminate inside the unit power box of the R1600. Figure
2.7 below indicates main power termination point on electrical block.
2.5.1 Phase Monitor:
Haskris Model R1600 is furnished with a three-phase
loss/reversal monitor as shown in Figure 2.8. This
phase monitor provides three-phase single-side
protection and monitors for phase reversal, phase
loss, and phase unbalance % as a function of input
voltage. If any fault exists, the red “FAULT’ LED
indicator will blink or be lit. After the fault is
corrected, there will be a 3 minute delay before the
unit restarts. Proper phase should be checked with the ‘Mode
Selector Switch’ in the center position (Stop Mode).
When the service disconnect switch is turned on, there will be a 3
minute delay before the unit starts.
Figure 2.7 High Voltage Panel
Figure 2.7 High Voltage Panel
Figure 2.7 High Voltage Panel
Figure 2.7 High Voltage Panel
Figure 2.8
Figure 2.8
Figure 2.8
Figure 2.8
Main Power Termination
Point on Electrical Block
Torque Field Line Connection:
120 INCH-LBS
-AND-
Field Ground Connection:
40 INCH-LB (6-10 AWG)
–OR-
50 INCH-LB (2-4 AWG)
!!!!