4. Commissioning
4.1 Notes for operation
Attention!
• Safety instructions
Observe the safety instructions set out in section 1 during operation.
• During operation,
be sure to avoid ...
– penetration of the device by foreign bodies or damp;
– aggressive or conductive substances in the immediate vicinity;
– covering over vent openings.
• Cooling
– The device heats up in operation and at the heat sink may reach temperatures of up to 100 °C. It poses a
risk of skin burns if touched.
– Cooling air must be able to flow through the device without restriction.
4.2 Initial commissioning
When the YukonDrive® has been installed as per section 2. and wired with all required voltage supplies and
external components as per section 3. , initial commissioning is carried out in the following steps:
Step
Action
Comment
1.
Installing and starting the PC software
see DriveManager 5 Installation Manual
2.
Switching on the control supply
see section 4.2.1
3.
Connecting the PC and drive controller
see section 4.2.2
4.
Parameter setting
see section4.2.3
5.
Controlling the drive with DriveManager 5
see section 4.2.4
Note:
Details concerning STO (Safe Torque Off) are not taken into account for initial commissioning, see manual 1007417
4.2.1 Switching on the control supply
For initialization and parameter setting, first switch on only the +24 V DC control supply. Do not yet switch on the AC
mains supply
Display readout after switching on the control supply
Table 37.1 Switch-on status of YukonDrive® (on connection of +24 V DC control supply)
D1
D2
Action
Explanation
Switching on the +24 V DC control supply
Initialization in progress
Initialization complete
Not ready for start
Note:
For details on the control supply refer to section 3.7 , “Connection of supply voltages”, starting on page 21.
Table 37.1