Figure 7.2 - Pipework Schematic No. 1
Example of a Milborne installation using domestic hot water with high temperature and low
temperature heating circuits.
*
See note below regarding pump control
*
The Milborne boiler has the facility to start and control 3 pumps.
It is therefore important when designing the heating system to allow pump number 3 to be assigned as the boiler
primary pump where required (see pipework schematic 1). In all other installations pump 3 will be assigned as the
low temperature heating circuit pump (see pipework schematic 2). Therefore where a primary system pump is
required the control system will not support a low temperature mixing circuit.