3.2 Inspecting the solution
The solution must be inspected after transport and before
installation.
The check must include the following:
•
Check if the solution has been damaged during transport. In
case of damage, contact the carrier immediately.
•
Make sure that the delivered solution corresponds to the order.
•
Check the position and sizes of pipes.
•
Tighten the various joints as they may have loosened during
transport.
3.3 Handling and lifting the solution
WARNING
Overhead load
Death or serious personal injury
‐
Do not stand under or close to hanging load.
‐
Follow local regulations when working at the solution.
WARNING
Overhead load
Death or serious personal injury
‐
Make sure that the lifting equipment is appropriate for
lifting the load before lifting the solution. See the
weight on the nameplate.
‐
Lift with caution. High centre of gravity may occur. Sol-
utions with a high centre of gravity are marked with a
warning.
Make sure that the forklift is not in contact with the con-
necting pipes.
The base frame of the solution has eyebolts for lifting
the solution with a lifting yoke.
•
Use lifting gear that ensures a vertical lift.
•
Use a safety strap to prevent the system from tilting.
1
2
Lifting the solution with a lifting yoke
3
Lifting the solution with a forklift
Pos.
Description
1
Lifting yoke
2
Lifting eyes
3
Forklift
Related information
4. Installation requirements
4.1 Location
The iGRID Pressure and Temperature Zone skid solution is
delivered as modules from factory. The solution can be placed in
buildings or technical rooms.
The building or technical room must be locked to prevent
unwanted access.