AVFM 6.1 Area-Velocity Flow Meter
2.
Hydraulic Dams
When the QZ02 sensor is to be mounted in front (upstream) of a hydraulic dam, or a Greyline
VD pipe dam, the sensor should be placed at least 20 inches in front of the dam:
3.
Pipe Grade
The pipe/channel in which the QZ02 sensor is mounted should not have a grade exceeding 3%:
Pipe / Channel
Side View
Grade 3%
QZ02
Sensor