RPV311
Distributed Multifunction Fault Recorder
Chapter 15: Installation
This chapter provides information about the product installation.
1
Handling the Goods
Our products are of robust construction but require careful treatment before
installation on site. This section discusses the requirements for receiving and
unpacking the goods, as well as associated considerations regarding product care
and personal safety.
Before lifting or moving the equipment you should be
familiar with the Safety Information chapter of this manual.
1.1
Receipt of the Goods
On receipt, ensure the correct product has been delivered. Unpack the product
immediately to ensure there has been no external damage in transit. If the product
has been damaged, make a claim to the transport contractor and notify us promptly.
For products not intended for immediate installation, repack them in their original
delivery packaging.
1.2
Unpacking the Goods
When unpacking and installing the product, take care not to damage any of the parts
and make sure that additional components are not accidentally left in the packing or
lost. Do not discard any CDROMs or technical documentation. These should
accompany the unit to its destination substation and put in a dedicated place.
The site should be well lit to aid inspection, clean, dry and reasonably free from dust
and excessive vibration. This particularly applies where installation is being carried
out at the same time as construction work.
1.3
Storing the Goods
If the unit is not installed immediately, store it in a place free from dust and moisture
in its original packaging. Keep any de-humidifier bags included in the packing. The
de-humidifier crystals lose their efficiency if the bag is exposed to ambient
conditions. Restore the crystals before replacing it in the carton. Ideally regeneration
should be carried out in a ventilating, circulating oven at about 115°C. Bags should
be placed on flat racks and spaced to allow circulation around them. The time taken
Содержание RPV311
Страница 2: ......
Страница 44: ......
Страница 99: ...RPV311 Chapter 5 Operation RPV311 TM EN 7 99 Figure 46 Status monitoring sequence ...
Страница 101: ...RPV311 Chapter 5 Operation RPV311 TM EN 7 101 Figure 47 Monitoring sequence ...
Страница 104: ...Chapter 5 Operation RPV311 104 RPV311 TM EN 7 Figure 49 Records monitoring sequence harmonics flicker and SOE ...
Страница 106: ...Chapter 5 Operation RPV311 106 RPV311 TM EN 7 Figure 50 Equipment settings monitoring sequence ...
Страница 107: ...RPV311 Chapter 5 Operation RPV311 TM EN 7 107 Figure 51 Circuit and channel settings monitoring sequence ...
Страница 108: ...Chapter 5 Operation RPV311 108 RPV311 TM EN 7 Figure 52 Relays PMU and MODBUS settings monitoring sequence ...
Страница 110: ...Chapter 5 Operation RPV311 110 RPV311 TM EN 7 Figure 53 General information monitoring sequence ...
Страница 142: ......
Страница 149: ...RPV311 Chapter 9 TW Fault Locator RPV311 TM EN 7 149 Figure 75 TW Fault Location example 1 ...
Страница 152: ......
Страница 160: ......
Страница 162: ......
Страница 164: ......
Страница 204: ......
Страница 265: ...Chapter 17 Technical Specifications RPV311 RPV311 TM EN 7 265 Figure 142 RPV311 Dimensions ...
Страница 275: ...Chapter 17 Technical Specifications RPV311 RPV311 TM EN 7 275 Figure 143 RA331 RA332 and RA333 dimensions ...
Страница 279: ...RPV311 Appendix A Equipment Log RPV311 TM EN 7 279 ...