GDS-68XP Operation & Maintenance Manual, Revision 3.4
Page 27
GDS-68XP STARTUP PROCEDURE
Before start up, review Chapter 4 (“Operation”) for information on operating modes and indications as
well as Chapter 6 (“Sequencer Controls and Indicators”). Figure 6-3 provides a handy reference to the red
and green LEDs (“L1” and “L2”) that indicate the current status of the sequencer processor.
ITEM
NOTES
1
MAKE SURE SAMPLE OUTLET IS CONNECTED
CLOSE INLET AND FILTER DRAIN VALVES
SAMPLE GAS CAN BE DEADLY. ALWAYS MAKE
SURE SAMPLE OUTLET IS DIRECTED TO A SAFE
AREA
2
SET SEQUENCE SWITCH TO “4”
SET FOR 4 HOUR SAMPLE
3
APPLY 24VDC POWER
L1, L2 FLASH
GASMAX DISPLAY ACTIVE
PUMP ON, PURGE AIR FLOWING
GDS-68XP WARMUP:
SENSOR 15 MINUTES
DURING WARMUP, PERFORM STEPS 4-5-6 BELOW
4
ADJUST FLOW METER VALVE FOR 0.5 LPM
ADJUST FOR ½ LPM PURGE AIR FLOW
5
CHECK TIME OF DAY CLOCK FOR TIMEZONE;
SET HOST NAME AND MEASUREMENT NAME;
SET ETHERNET NETWORK PARAMETERS
CHANGES TO NETWORK SETTINGS ARE NOT
RECOGNIZED UNTIL NEXT POWER-UP
SEQUENCE. RETURN TO STEP 3 IF CHANGED
6
OPTIONAL: VERIFY 4-20MA SIGNAL TO REMOTE
DCS OR PLC
USE DIAGNOSTICS MENU TO FORCE CHANNEL 2
OUTPUT TO 4MA / 20MA AND VERIFY READING
ON RECEIVING DEVICE
GDS-68XP COMPLETES FIRST SEQUENCE AND ENTERS PURGE / HOLD MODE:
OUTPUT = “FLOW FAULT”, L2 (GREEN) FLASHING
7
OPEN SAMPLE INLET VALVE
VERIFY PRESSURE ON PRESSURE GAUGE
8
PRESS “BYPASS” AND
ADJUST REGULATOR
FOR
0.5 LPM SAMPLE GAS FLOW
DO NOT RE-ADJUST FLOW METER VALVE
RAW SENSOR OUTPUT SHOULD INCREASE IF
TARGET GAS PRESENT
9
PRESS “RUN” TO EXIT BYPASS
CLOSES SAMPLE VALVE AND RETURNS
SEQUENCER TO PURGE/HOLD MODE
GDS-68XP COMPLETES PURGE / HOLD
GDS-68XP WILL RUN NEW SAMPLE SEQUENCES APPROXIMATELY EVERY FOUR HOURS
ALLOW NEW UNIT TO RUN SEVERAL SEQUENCES BEFORE PROCEEDING
10
PERFORM SENSOR CALIBRATION
SEE CHAPTER 7
GDS-68XP INSTALLATION COMPLETE