Scope of Work/Materials
13850 (28 31 00) - 5
Bid No.041818-Installation of New Fire Alarm System at Adams Elementary School
c.
Prepare using AutoCAD.
d.
Prepare to scale 1/8 inch = 1’-0”, unless otherwise required by the Architect or
Engineer.
e.
Show equipment and device locations.
f.
Show wiring information in point-to-point format.
g.
Show conduit routing, if required by the AHJ.
3.
Title Block: Provide on each sheet and include, at a minimum, the following:
a.
Project name.
b.
Project address.
c.
Sheet name.
d.
Sheet number.
e.
Scale of drawing.
f.
Date of drawing.
g.
Revision dates, if applicable.
4.
Control Panel: Provide sheet that details exterior and interior views of control panel and
clearly shows associated wiring information.
5.
Annunciator Panels: Provide sheet that details exterior and interior views of annunciator
panels and clearly shows associated wiring information.
E.
Certification: Submit with equipment submittals and shop drawings, letter of certification from
Gamewell-FCI
, indicating proposed engineered system distributor is an authorized
representative in good standing of the equipment supplied. Include a copy of at least two (2)
certified technician E3 system training certificates.
F.
Project Record Drawings:
1.
Submit complete project record drawings within 14 calendar days after acceptance test.
2.
Project record drawings shall be similar to shop drawings but revised to reflect changes
made during construction.
G.
Operation and Maintenance Manuals:
1.
Submit complete operation and maintenance manuals within 14 calendar days after
acceptance test.
2.
Operation and maintenance manuals shall be similar to equipment submittals but revised
to reflect changes made during construction.
3.
Include
factory’s standard installation and operating instructions.
1.6
QUALITY ASSURANCE
A.
Codes and Standards:
1.
NFPA: System shall comply with the following NFPA codes and standards:
a.
NFPA 12.
b.
NFPA 13.
c.
NFPA 15.
d.
NFPA 16.
e.
NFPA 16A.
f.
NFPA 70.
g.
NFPA 72.
h.
NFPA 90A.
i. NFPA 90B When smoke control is required by code.