Verify ac input voltages
3-3 Config
.:
Phase-to-Phase:
3x400 Vac, -22 % / +15 %
Phase-to-Neutral:
230 Vac, -22 % / +15 %
3.3.3 Step 3
Verify the voltage between neutral and ground
0–2 Vac
3.3.3 Step 4
Verify dc voltage at battery cabinet switch.
+360 V and – 360 V
3.3.3 Step 5
Verify that
FAST FUSES (SEMICONDUCTOR
FUSES)
are in place between the battery and
the UPS. For example, the Bussmann “FWH”
fuse.
Verify that neutral is always connected
Check diagram for proper connection
Verify that mains ac power CBs are in the OFF
position, that the battery CB is OFF, and that all
external switches are OFF.
If you have installed a maintenance bypass
switch, verify that it is set to Normal (Off)
Connect the battery box or boxes to the UPS
now.
Comments on site preparation
–
electrical: __________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
I n i t i a l S t a r t u p
Apply ac power and measure dc voltage
+405 Vdc and –405 Vdc
3.5 Steps 1, 2
Turn the battery switches On to conduct
3.5 Step 3
Verify module configuration and redundancy
Match specifications
3.6, Step 3
Check the controller definition of total Ah of the
batteries
Match installed batteries
3.6, Step 5
Verify proper time zone
Should be accurate
3.6, Step 6
Enter IP address of UPS into the controller
Obtain from system admin
Comments on initial startup: __________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
T e s t i n g
Measure output voltage with all ac inputs Off
230 V or as specified
Measure output voltage after cold start
230 V or as specified
Measure ac input voltage under load
Phase-to-phase and phase-to-neutral
voltage no less than 2% below no-load
values
Check total system load
3-3 Config
: Output current is within
system specifications
L1= ___A; L2= ___A; L3=___A
Check correct operation
No alarms or fault indications
Check IP communication with controller
Reach controller from browser
Comments on testing, if any: