COMMISSIONING - 3
3.1.4
BOILER INSPECTION AND INITIAL FIRING
OIL BURNER
Note:
Always place the highest value nozzle (engraved on the side of the nozzle) into the low fire oil supply port
in the manifold.
1. Ensure that the boiler has been washed out after installation. It is advisable to conduct a water
analysis before operating the boiler.
Examine the probes in the water bottle and the boiler shell and record their lengths.
Replace any damaged probes.
2. Remove the burner and check the electrodes have not been damaged and that their settings
are correct. If the burner is fitted with a flame detector, remove it and check for damage.
3. Replace the burner and reconnect the copper oil line(s) to the oil nozzle assembly (and gas
connection on Dual Fuel burners), ensuring these connections are tight. Reconnect the
ignition leads and replace the flame detector.
4. (DUAL FUEL ONLY) Ensure that the gas supply isolation valve is closed. Check that the oil
supply valve is open.
5.
Check the rotation of the oil pump motor. Ensure that the oil supply flow and return valves are
open. Bleed the oil pump.
6. Ensure all wiring connections are correct and that all terminal screws are tight.
7.
A barometric type draught stabiliser, if fitted in the flue, should be set for a draught of
- 0.025 mbar to - 0.05 mbar of water bottle pressure with the burner off.
8. Open all the valves in the feedwater line.
Close the isolating valve on the discharge side of the feedwater pump. Remove the priming
plug from the pump head and slowly fill the pump with water. Replace the priming plug and
tighten securely.
9. Check the correct rotation of the feedwater pump on the motor fan cover.
Start the feedwater pump and check the direction of rotation.
DO NOT ALLOW THE PUMP TO RUN DRY.
10. Open all the valves in the water feed line.
Switch on the feedwater pump motor and fill the boiler (see
Section 4.5 - Filling the boiler
).
The operation of the pump controls should be checked by using the boiler blowdown valve
(located at the rear of the boiler). When the water level gauge (sight glass) is reading two
thirds full, the pump will stop.
11. Open the boiler blowdown valve and slowly drain the boiler. When the water level falls below
the PUMP ON probe, the pump should start. If the pump does not start, check the probe
connections.
12. Close the boiler blowdown valve.
13. Fit oil pressure gauge to oil pump to verify oil pressure.
14. Start the burner as detailed in
Section 3.5 - Starting the burner
. Allow time for the fuel pump
to prime itself.
CONTINUED ON NEXT PAGE
Содержание VMP Series
Страница 8: ...VMP IOMM 2018 2 Fulton Ltd Page VIII...
Страница 25: ...VMP IOMM 2018 2 Fulton Ltd Page 17 INSTALLATION 2 Figure 10 Electrical Customer Terminal Connections...
Страница 30: ...VMP IOMM 2018 2 Fulton Ltd Page 22...
Страница 66: ...VMP IOMM 2018 2 Fulton Ltd Page 58...
Страница 100: ...VMP IOMM 2018 2 Fulton Ltd Page 92...
Страница 102: ...VMP IOMM 2018 2 Fulton Ltd Page 94 APPENDIX C...