140.925-IOM (APR 2019)
Page 6
XLP3 EVAPORATIVE CONDENSERS
INSTALLATION
Figure 2 — Two-Piece Lift
L
H
L
H
Rigging of Upper Coil Section
Rigging of Lower Fan Section
center of gravity
8. Secure the hose connecting the sections of the pump dis-
charge pipe with the hose clamps provided.
9. On units with more than one casing, install the remaining
casings using the same procedure as the first. When installing
two or more casings, on the basin section, sealer tape must be
applied to both cross flanges (see Figure 3).
10. On units operating with a remote sump tank, install a bleed
line with valve between the system circulating pump discharge
riser and a convenient drain. Locate the bleed line in a portion
of the riser piping that drains when the pump is off. Units that
are furnished with a factory-installed circulating pump include
a bleed line with valve.
CAUTION
Before proceeding, bolt the basin sections securely to the
supporting steel.
Figure 3 — Sealer Tape Application
Figure 4 — Fastening of Upper and Lower Sections
Figure 5 — Section Alignment Using Drift Pins