Commissioning Checklist
FORUM Handling Tools strongly recommends accomplishing the SSW-40 commissioning with the
FORUM Handling Tools Commissioning Service.
Read manual before first use!
OK
Check crew is aware of all danger regarding handling the FORUM Handling Tools tool.
OK
Go through manual with crew.
Carry out following checks prior the use of the FORUM Handling Tools SSW-40:
Scope of supply
OK
Crosscheck all delivered parts.
Pneumatic and lubrication
OK
Operating pressure
Min 90 psi to Max 160 psi
Min 6.20 bar to Max 11.03 bar
OK
Air filter and regulator
Lubricated and de-watered, air regulator and lubricator installed.
OK
Check Air Supply line is connected.
OK
Check for leaks in the pneumatic system.
OK
Apply grease to all greasing points.
OK
Check oil level in gear box.
Installation and function
OK
Backup lines are installed.
[optional]
Snub-Line-Sensor is installed on the correct side.
Spin In = left hand side; Spin out = right hand side
OK
Check for correct location of the SSW-40.
OK
Check SSW-40 turns its rollers by air pressure.
OK
Check SSW-40 lifts and lowers by air pressure.
Info
This commissioning checklist contains only
essential points for an internal commissioning
(e.g. after storage). Check at least the points on
your SSW-40, which are mentioned above. For
further questions or commissioning checklist
templates, please contact the Technical Support
from FORUM Handling Tools.