Ensemble Commissioning: Installer Toolkit Communications
© 2020 Enphase Energy Inc. All rights reserved.
July 24, 2020
___________Installer Initials: All steps complete on this page
8
G.3.1. Grid profile will be updated.
G.3.2. Tariff will be updated only if the single rate was set in step E.
G.3.3. PV microinverters will be provisioned.
G.3.4. Enpower will be provisioned.
G.3.5. Encharge microinverters will be provisioned.
G.3.5..1.1 During provisioning, the status flows as follows:
G.3.5..1.1.1 Discovered / not discovered (Installer Toolkit is able to
discover the device using Bluetooth Low Energy (BLE).
G.3.5..1.2.1 Waiting for provisioning (The initial communication is being
established. Installer Toolkit is sending network information to
Encharges and Enpower using BLE).
G.3.5..1.3.1 Waiting for acknowledgement (Envoy is trying to
communicate to the Encharges and Enpower using the wireless
2.4 GHz radio).
G.3.5..1.4.1 Provisioned (Envoy can communicate with the Encharges
and Enpower).
G.3.5..2.1 Once provisioning is complete, click
Done
.
H. Confirm that the Encharge batteries are communicating with the Envoy by checking Installer
Toolkit step 2:
Device & Array
. Encharge batteries should display “communicating” as
follows: