background image

InsulGard System Installation and Start Up Guideline 

 

29 

Appendix 1.  PD System Installation Checklist 

 

Procedure 

Result 

Installation: 

Unpack InsulGard and sensors, verify packing lists and 
equipment condition  

 

Verify that it is the system designated for the object. Temporal 
label on the front panel of an InsulGard shows the object 
name. The serial number on the InsulGard label should 
coincide with InsulGard serial number in database software for 
this object.  

Object name: 
Object nameplate information:  
Insulgard serial number  

Verify power voltage designated on the InsulGard label. 

(Don’t 

use UPS power, beware of autotransformers, use insulating 
transformer instead if needed.). 

U= 

Identify sensor placement specifics. For switchgear line the 
PD sensor placement needs to coincide with worksheet filled 
out at the time of order entry. For motors it usually should 
coincide with the configuration table in Figure 1-12   

Link

. 

 

Proceed with installation and cable termination in accordance 
with corresponding Manuals and 

“PD Sensor Configuration” 

Table.4 or 5 in Appendix 2  

Link

. 

 

Circuits Integrity Check 

Check External Ground being brought to the Insulgard (right to 
the Door mount unit or to InsulGard panel / enclosure). 

 

Measure power supply voltage and write down in the Table 1 
in Appendix 2. (If insulating transformer was used for power 
supply, check voltage only between Line and Neutral) 

Table 1 - 

Link

 

Check IPDS sensor installation. Make sure the sensors are 
reliably grounded. Check clearance between sensors with 
jumper cable installed on different phases and also between 
them and grounding surfaces. Keep clearance between signal 
cables and HV side. Rule of thumb: clearance should be the 
same as IPDS height for given voltage class. 

 

Check RFCT sensor installation: proper direction to Ground 
the arrow on the sensor label and that the wires grounding 
feeder shields don’t touch grounding surface before they go 
through the sensor. 

 

 

10 

Check RTD-6-PD sensor board installation (only for rotating 
machines). Fill out the Table 3 in Appendix 2. 

Table 3 for rotating machines - 

Link

 

11 

Check proper connection of PD sensors to the Sensor 
Interface Board. Measure resistance of each PD sensor 
across board terminals and write down in the Table 4 or 5 in 
Appendix 2. 

Table 4 for rotating machines - 

Link

. 

Table 5 for switchgears - 

Link

. 

12 

Check external Temperature and Load (if installed) sensors 
resistance and fill out Table 2 in Appendix 2. Verify 
reasonable reading of the temperature and humidity on the 
InsulGard display after its power ON. 

Table 2 - 

Link

 

T =  
H =  

Insulgard Configuration Verification 

 

13 

Software and database 

corresponding to the object

 have 

been installed. Make sure the Modbus address and baud rate 
are correct. 

 

14 

Verify Communication with the InsulGard through local port. 
Set the correct date and local time. 

 

Содержание InsulGard

Страница 1: ...InsulGard InsulGard System Installation and Start Up Guideline Version 1 April 2018...

Страница 2: ...ear line 18 2 START UP 19 2 1 Getting ready 19 2 2 Insulgard Software Installation and Communication Establishing 19 2 3 Verifying Correcting Configuration 21 2 4 PD Channel Calibration Verification 2...

Страница 3: ...shipping damage Verify that it is exactly the device designated for this project Identify place and way of sensors and InsulGard installation Identify and verify proper power and communication lines...

Страница 4: ...ection 1 2 Link and their connection to Insulgard monitor Also some external interfaces can be connected to the Insulgard to remotely get information about the monitor and monitored object condition T...

Страница 5: ...installed sensor The maximum distance allowed between the PD sensors and the InsulGard coaxial cables length is 150 feet a For a motor the best location of InsulGard enclosure installation is as close...

Страница 6: ...e inside InsulGard for 230VAC application Time Lag 100mA 250VAC 5X20mm type 5ST by BEL Fuse Inc Catalog 5ST 100 Fuse on the panel Fast Acting 3 0A 250VAC 5x20mm type 5MF by Bel Fuse Inc Catalog 5MF 3...

Страница 7: ...cable from the Sensor Interface Board on the left side of the monitor Use latching levers on both sides of the connector see picture below in small steps to lift the connector and then pull the conne...

Страница 8: ...els 1 15 PD sensors must be connected accordingly For motor generator application connect IPDS sensors on phases A B and C starting with channel 1 and then connect RTD PD sensors For switchgear applic...

Страница 9: ...connection and connection to relays to RS485 and 4 20mA interfaces Use green plugs on the right side of the InsulGard Figure 1 6 and 1 8 The green plugs can be wired when the InsulGard is not install...

Страница 10: ...face port 1 2 Installation of the InsulGard Sensors Monitored object and InsulGard must be de energized The best way to de energize InsulGard is to de energize the incoming power supply line On a pane...

Страница 11: ...direction of the arrow on the sensor s label to Ground Be sure that the wires grounding feeder shields don t touch grounding surface before they go through the sensor Figure 1 10b a Coax cable connec...

Страница 12: ...e metering verify proper reading on customer s metering system 2 Auxiliary sensors a TS External Temperature sensor 3 wire 100 Ohm platinum RTD in protecting shell For rotating machines using spare 10...

Страница 13: ...uxiliary sensors connection a Units mounted on a panel and inside enclosures will generally have external temperature and humidity sensors Check that external sensors are properly wired to the Sensor...

Страница 14: ...connection for a motor is shown in Figure 1 12 The sensors are a Three IPDS sensor installed in the motor terminal box b One RTD 6 PD Sensor Board installed in motor RTD terminal box For large motors...

Страница 15: ...nel Sensor Sensor designation in data base 1 IPDS Phase A CC_A 2 IPDS Phase B CC_B 3 IPDS Phase C CC_C 4 RTD 01 PD 1 output of RTD 6 sensor RTm01 5 RTD 02 PD 2 output of RTD 6 sensor RTm02 6 RTD 03 PD...

Страница 16: ...emote communications if required 1 2 conductor shielded wire for 4 20 ma output if required 1 6 conductor cable suitable monitoring of dry contacts for system status low alarm and high alarm minimum 2...

Страница 17: ...e sensor 5 Auxiliary sensors installation in the motor termination box a Install external Humidity sensors b Install external air Temperature sensor if supplied and no winding temperature RTD platinum...

Страница 18: ...dded in the Sensor Interface Board of the door mounted InsulGard External sensors are not required with this type of installation For PD sensors installation and their connection to InsulGard refer to...

Страница 19: ...fication procedure considered optional but highly recommended Print and use PD system installation checklist from Appendix 1 as a guideline for StartUp and Commissioning procedures and a core of the i...

Страница 20: ...ction has been chosen as the simplest and most reliable local communication You may have to install communication software first Refer to the corresponding paragraph of InsulGard User Manual 2 Start I...

Страница 21: ...ect the actual sensors configuration see Appendix 5 After correcting settings in software press Backup Settings in Unit Settings tab 6 Send correct settings by pressing Send Settings to Device button...

Страница 22: ...erator used set the generator pulse parameters Pulse Magnitude 10 Volt Pulse Width 100 nanoseconds Pulse repetition rate 1 10 kHz Magnitude and pulse repetition parameters are not critical Pulse width...

Страница 23: ...from Communications tab of the InsulGard software A measurement time is proportional to the number of active channels and will take approximately 1 5 minutes for maximum 15 active channels 2 Download...

Страница 24: ...cedure see above hasn t been performed and the equipment already energized it is possible to verify what PD sensors are connected to the Sensor Interface Board Check that PD sensor coax cables is not...

Страница 25: ...on For typical applications 50Hz 10Hz enter 275 degrees shift Automated phase shift measurement can be done only from the InsulGard keypad 1 Press Set key to enter the setup mode The password prompt s...

Страница 26: ...ngs from Device to synchronize settings in the monitor and software Click Update Data base with Device settings when phase shift settings discrepancy will be displayed 10 In InsulGard Unit Settings Ta...

Страница 27: ...that metering CT ratio is always Ict 5 If rated current was entered in the settings calculate Current Coefficient and enter it manually as CK 2 2 Ict If rated current was not changed in the settings f...

Страница 28: ...an take as long as 6 minutes After finishing measurements InsulGard will return to scrolling mode and will be ready for the next measurement 5 Repeat step 4 three more times 6 Once all measurements ar...

Страница 29: ...ansformer was used for power supply check voltage only between Line and Neutral Table 1 Link 8 Check IPDS sensor installation Make sure the sensors are reliably grounded Check clearance between sensor...

Страница 30: ...ase Line Measurements on Energized Equipment 20 StartUp 1 Software installed database corresponds to the object 2 Phase reference measurement is performed phase shift calculated 3 Load channel calibra...

Страница 31: ...te If insulating transformer was utilized for power supply check voltage between Line and Neutral only Table 2 Check Temperature and Load for motors only sensors Auxiliary sensor Resistance between co...

Страница 32: ...iguration for switchgear line The table below helps to avoid errors at PD sensor installation their cables termination and for report preparation Ch Sensor designation in database 1 Sensor measured re...

Страница 33: ...significant reprogramming of database software and InsulGard firmware settings and can lead to errors InsulGard ID SWG 72YJ573 VS 6 Insulgar d Channe l Sensor Type CC Coupling Capacitor IPDS CT CT on...

Страница 34: ...Guideline 34 Insulgard Settings for Channels in database have same designations of the sensors as in the above table If the sensors positions were changed at installation the sensor designation in th...

Страница 35: ...InsulGard System Installation and Start Up Guideline 35 Appendix 4 Door cutout dimensions for Door mount InsulGard Blue color shows InsulGard front panel dimension...