InsulGard System Installation and Start Up Guideline
23
GKI-2 test generator connected to IPDS HV contact
Connect test generator to phase B feeder
terminal
Figure 2-1
Calibration Verification steps
1.
Switch the generator ON and run “Single Measurement” from Communications tab of the InsulGard software. A
measurement time is proportional to the number of active channels and will take approximately
1.5 minutes for
maximum 15 active channels.
2.
Download data from InsulGard by pressing “Read the Latest Device Records” button. Observe phase-resolved
data from this measurement from the
“Graphs and Report” Tab. An example of expected data is shown in the
Figure below.
~2V output signal on
IPDS on phase C
RFCT