InsulGard System Installation and Start Up Guideline
30
15
Change the configuration of the database to the actual
sensors configuration
PD sensors configuration table
16
Upload the updated configuration to the InsulGard and save
as Back Up
PD Channel Calibration/Verification
(Optional but highly recommended).
17
Prepare monitor by setting calibration configuration
18
Perform calibration/check of the sensors and InsulGard
functionality by injecting signal to every sensor from pulse
generator. Write down measured signal magnitudes in the
Table 4 or 5 in Appendix 2.
Save calibration data records.
Table 4 or 5 in Appendix 2.
Calibration data records
19
Restore monitor configuration and erase device memory.
This will conclude installation procedure
Base Line Measurements on Energized Equipment
20
StartUp
:
1. Software installed, database corresponds to the object -
2.
Phase reference measurement is performed, phase
shift calculated
3. Load channel calibration is performed at load - xx%
4. Settings downloaded to the database software -
5. InsulGard memory cleared
–
Phase shift =
21
Base Line measurements:
1. Base line measurements performed in Test Mode
–
2. Data downloaded into database
–
3. Data analyzed, necessary changes to the settings have
been made -
4. InsulGard set in Normal Saving Mode and left for
monitoring
22
Customer training
1. Install software to the customer computer
2. Synchronize databases by copying your database to the
customer computer or downloading settings and data to a
customer computer from the Insulgard
3. Train customer to operate InsulGard from his computer and
how to transfer data for analysis.
4. Teach how to transfer data for analysis
23
Prepare and submit the installation/commissioning report