InsulGard System Installation and Start Up Guideline
3
Installation Staircase
Print and use “PD system installation checklist” from Appendix 1-
for StartUp and
Commissioning as a guideline and a core of installation report.
Done!!!
Begin
with
Check contents against
the packing lists and the
equipment condition for
shipping damage. Verify
that it is exactly the device
designated for this project
Identify place and way
of sensors and
InsulGard installation
Identify and verify proper power
and communication lines to be
connected to the InsulGard
Actual installation
Sensors and external
lines connection check
Software Installation,
communication test
Sensors calibration/
verification
Start Up and base line
measurements on
energized equipment
Customer training
and database
synchronisation
Report on installation/
commissioning