Commissioning
Copyright © 2007-2010 Eaton Corporation. All Rights Reserved.
IPN 997-00012-52D July 2010
89
Test
Test procedure
Adjustment
•
Monitor the battery current to ensure the
Battery Current
Limit
control process is operating.
Current Share
Note 6
•
View the individual rectifier currents with the SC200 or
SC100 or DCTools/Web.
•
Ensure the currents are all at 0 amps.
•
Connect load to the system.
•
Ensure that all rectifiers share the load evenly and any
variation is within specification.
None
Battery Test
•
Set the
Battery Test Interval
to 0 days.
•
Set the
Battery Test Duration
to 30 minutes
•
Set the
Battery Test Termination Voltage
to a value
approximately 2 volts below the float voltage.
•
Connect load to the system.
•
Start the
Battery Test
.
•
Ensure the SC200 or SC100 indicates that a
Battery Test
has
started.
•
Wait until the system voltage reduces below the
Termination Voltage
.
•
Confirm the
Battery Test
fails.
•
Ensure the
Battery Test Fail
alarm is displayed on the SC200
or SC100.
•
Ensure the
Battery Test
stops and the system voltage
returns to the float voltage setting.
•
Clear the
Battery Test Fail
alarm in DCTools/Web.
•
Set the
Battery Test Duration
to 1 minute.
•
Set the
Battery Test Termination Voltage
to a value
approximately 10 volts below the float voltage.
•
Connect load to the system.
•
Start the
Battery Test
.
•
Ensure the SC200 or SC100 indicates that a
Battery Test
has
started.
•
Wait for the
Battery Test Duration
time to expire.
•
Confirm the
Battery Test
passes.
•
Ensure the
Battery Test
stops and the system voltage
returns to the float voltage setting.
•
Reset the
Battery Test
settings to the original values.
None
Low Voltage
Disconnect –
Manual Operation
Note 7
•
Set the LVD manual control to
CONNECT
.
•
Ensure the LVD contactor is connected.
•
Ensure the SC200 or SC100 displays an
LVD Manual
alarm.
•
Ensure the I/O board LVD LED is on.
•
Set the LVD manual control to AUTO.
•
Ensure the SC200 or SC100 shows no LVD alarms.
•
Ensure the I/O board LVD LED is on.
•
Set the LVD manual control to
DISCONNECT
.
•
Ensure the LVD contactor disconnects.
•
Ensure the SC200 or SC100 displays an LVD Manual alarm.
•
Ensure the I/O board LVD LED is off.