INSTALLATION
4–29
4.5.2 Control/Interface Wiring
Connect the two control wires provided with the UPS CSA Cabinet to the UPS cabinet
terminal block TB2, terminals 11 and 12. Terminal block TB2 is located inside the UPS
cabinet, in the customer cable entry section (Figure 4–3).
4.5.3 Checks After Installation
After installing the UPS CSA Cabinet, make the following checks:
1. Ensure that all power and control wires have been properly connected and securely
tightened.
2. Check the rating on the upstream protective devices, and make certain that they are
compatible with the UPS CSA Cabinet requirements.
3. Verify that the input voltage to the HA33D UPS CSA Cabinet is 600 Vac or that the
input voltage to the HA33F UPS CSA Cabinet matches the requirement shown on
the HA32A UPS nameplate, located inside the door of the UPS cabinet.
4. Verify that the output voltage of the HA33D/F UPS CSA Cabinet is compatible with
the UPS input voltage requirements (UPS main ac input and/or bypass ac input).
Check both nameplates.