INSTALLATION REFERENCE CHECKLISTS
Check Off
Function
Task
Configuration Layout
Plan the configuration layout using the following
placement order (left to right): UPS Battery Cabinet(s),
UPS cabinet, UPS Auxiliary Cabinet, UPS CSA
Cabinet, and UPS Distribution Cabinet.
Floor Marking
Mark the outside dimensions of the cabinet
configuration and the floor cutouts on the floor with
tape so that placement and any floor cutouts will be in
the correct place.
Floor Cutouts
On a raised floor, ensure that floor tile cutouts are
provided for cool air supply and cabling. Refer to the
HA3000 20-80 kVA Uninterruptible Power System
Installation Drawings
(EK-HA32X-ID) for the cable
entry areas on the UPS cabinet, the UPS Battery
Cabinet, and the UPS Distribution Cabinet.
CAUTION: If perforated tiles are used for cooling,
ensure that air restricting baffles are not installed
beneath them.
Inside Delivery
Route
Ensure that there is an unobstructed inside delivery
path to the final installation position. Ensure that
elevators, ramps, and flooring along this path can
handle the equipment weights and dimensions.
1.1.2 Delivery/Handling
The customer’s responsibilities during delivery/handling are listed below.
Check Off
Function
Task
Site Delivery
Coordination
Assist Digital Services in assuring proper delivery and
placement of the HA3000 series cabinets.
Configuration
Assembly
Assist Digital Services in removing the appropriate
side skins and cover plates before the cabinets are in
their final position.
Final Assembly
Assist Digital Services in replacing all exterior skins.
Check to ensure that all cabinets are complete.