6-6-8 Power cell installation
The power cell shall be handled carefully and be confirmed that it is not damaged or
affected by shock after being unpacked;
Simple forklift can be used to move and lift the power cell. At least two persons are
required for cooperation during installation.
The power cell shall be completely thrust into the fixing support slot;
After the power cell is installed, M6 screws are required to fix the corners, as shown in
Fig. 6-17.
Fig.6-17 Power cell installation (215A)