Figure 56. Remove Rails from the Rack
Install the Cable Management Tray
Installation of the 1U cable management tray must be performed during a scheduled maintenance window when the Storage Center
system is unavailable to the network.
Steps
1.
If the expansion enclosure rails are installed, push in the blue tab on the rails before installing the 1U cable management tray.
Figure 57. Push in Blue Tab on Expansion Enclosure Rails
2.
Align the rails so that the UP arrow is pointed in the correct direction and the end of the rail labeled FRONT is at the front of the
rack.
3.
Insert the alignment pins of left and right rails into the mounting holes at the front and back of the rack.
4.
Secure the rails by installing 8-32 x 0.75 in. screws into the holes at the front and back of the rails.
50
Replacing SCv360 Expansion Enclosure Components