System Installation and Configuration
96-30051-001 Rev. D3
DDN SFA12K (SFA OS 2.3.1) Hardware Installation & Configuration Guide | 9
1.
Installation Overview
1.
Unpack the system (Section
2.
Install the controllers, BBU, ATS, and disk enclosures into rack (Section
3.
Connect the disk enclosures to controllers (Section
4.
Install the disk modules into the disk enclosures (Section
5.
Connect the cables between controllers, BBUs, ATSs, and PDU (Sections
and
).
6.
Configure the ATSs (Section
7.
Configure the network ports via the serial console (Sections
to
8.
Configure the BBUs (Section
9.
Validate the hardware and configure subsystem settings (Section
10.
For E-platforms, use either a VNC viewer or SSH to access the preconfigured Virtual
Machines (Section
For block-storage configurations, create storage pools, virtual disks, spare pools, and
presentations (Sections
to
2.
Unpacking the System
If your system is already installed in the racks, refer to the
DDN 42U/45U 28" Wide Rack
Installation and Service Guide
for instructions on removing the system from the shipping
crate and positioning the system.
Before you unpack your SFA12K, inspect the shipping containers for damage. If you detect
damage, report it to your carrier. Retain all boxes and packing materials in case you need to
store or ship the system in the future.
2.1
Packing List
The SFA12K ships with the following:
• Two controllers with rackmount kit
• Two battery backup units (BBU) with rackmount kit
• Two automatic transfer switches (ATS) with rackmount kit and serial cable
• InfiniBand ICL cables (3 cables for SFA12K-20, 12KXE, 12K-20E; 6 cables for SFA12KXi,
12KX, and 12K-40)
• Two USB cables (BBUs to controllers)
• SAS cables
• Disk enclosures with rackmount kit