2 How to Install
2.1 Installation
2.1.1 How to Install Option in Frequency
Converter
Items required for installing a fieldbus option in the
frequency converter
•
The fieldbus option
•
Fieldbus option adaptor frame for the FC Series.
This frame is deeper than the standard frame to
allow space for the fieldbus option beneath
•
Strain relief (only for A1 and A2 enclosures)
EtherNet Port1
EtherNet Port2
MCA
121
Option A
EtherNet/IP 130B1
119
MS
MS1
MAC-00-1B-08-00-00-22
MS2
SW.ver.
130B
T797.10
Illustration 2.1 Fieldbus Option Adaption Frame
Illustration 2.2 Strain Relief for A1 and A2 Enclosures
Instructions
1.
Remove LCP panel from the FC Series.
2.
Remove the frame located beneath and discard it.
3.
Push the option into place. The Ethernet
connectors must be facing upwards.
4.
Remove knock-out on the fieldbus option adaptor
frame.
5.
Push the fieldbus option adaptor frame for the FC
Series into place.
6.
Replace the LCP and attach cable.
NOTE
Do not strip and ground the Ethernet cable via the strain
relief-plate! The grounding of screened Ethernet cable is
done through the RJ-45 connector on the option.
NOTE
After installing the MCA 123 POWERLINK option, set
8-01 Control Site
to:
[2] Control word only
or
[0] Digital and
ctrl. word
.
8-02 Control Word Source
to:
[3] Option A
2.1.2 Network
It is important that the media chosen for Ethernet data
transmission meets the required properties. Usually CAT 5e
and six cables are recommended for industrial applications.
Both types are available as Unshielded Twisted Pair and
Shielded Twisted Pair. Generally, shielded cables are
recommended for use in industrial environments and with
frequency converters.
A maximum cable-length of 100 m is allowed between
network devices.
How to Install
MCA 123 POWERLINK Operating Instructions
MG92C102 - VLT
®
is a registered Danfoss trademark
5