3
|
Components
Service manual
82
250D7Y1B
Sky Air Advance-series
ESIE19-13A – 2020.05
1
Access the back side of the switch box, see
2
Turn ON the power of the unit.
3
Measure the voltage between the following wires on the inverter PCB.
Result:
All measurements MUST be 400 V AC.
▪
L1B–L2B
▪
L1B–L3B
▪
L2B–L3B
b
a
c
a
L1B
b
L2B
c
L3B
Is the measured voltage correct?
Action
Yes
81] of the PCB and
continue with the next procedure.
No
Continue with the next step.
4
Measure the output voltage between the following wires on the noise filter
PCB.
Result:
All measurements MUST be 400 V AC.
▪
L1B–L2B
▪
L1B–L3B
▪
L2B–L3B
Is the measured output voltage on the
noise filter PCB correct?
Action
Yes
Correct the wiring between the inverter
PCB and the noise filter PCB, see
137].
No
Perform a check of the noise filter PCB,
see
To check the HAP LED of the inverter PCB
Prerequisite:
First perform a power check of the inverter PCB, see
81].
1
Locate the HAP LED on the inverter PCB.
Содержание Sky Air Advance RZA200D7Y1B
Страница 1: ...Service manual Sky Air Advance series RZA200D7Y1B RZA250D7Y1B ...
Страница 190: ......
Страница 191: ......
Страница 192: ...ESIE19 13A 2020 05 Copyright 2020 Daikin Verantwortung für Energie und Umwelt ...