9
|
Electrical installation
Installer reference guide
125
EPRA08~W1 + ETVH/9W
Daikin Altherma 3 H MT F
4P634886-1 – 2021.03
Smart Grid contact
Smart Grid operation mode
1
2
0
1
Forced off
1
0
Recommended on
1
1
Forced on
The use of a Smart Grid pulse meter is not mandatory:
If Smart Grid pulse meter is…
Then [9.8.8]
Limit setting kW
is…
Used
([9.A.2]
Electricity meter 2
≠
None
)
Not applicable
Not used
([9.A.2]
Electricity meter 2
=
None
)
Applicable
In case of low voltage Smart Grid contacts
Wires (Smart Grid pulse meter): 0.5 mm²
Wires (low voltage Smart Grid contacts): 0.5 mm²
[9.8.4]=3 (
Benefit kWh power supply
=
Smart grid
)
[9.8.5]
Smart grid operation mode
[9.8.6]
Allow electrical heaters
[9.8.7]
Enable room buffering
[9.8.8]
Limit setting kW
The wiring of the Smart Grid in case of low voltage contacts is as follows:
14
13
S11S
6
5
S4S
4
3
X5M
S10S
10
9
a
2
1
a
Jumper (factory-mounted). If you also connect a safety thermostat (Q4L), replace
the jumper with the safety thermostat wires.
S4S
Smart Grid pulse meter
1
/S10S
Low voltage Smart Grid contact 1
2
/S11S
Low voltage Smart Grid contact 2
1
Open the following (see
"7.2.5 To open the indoor unit"
1
Top panel
1
2
3
2
User interface panel
3
Upper switch box cover
2
Connect the wiring as follows: