4.3.
Preparing the Cooling Unit for the Connection of
Water-Cooled Cabinets
WARNING
To protect from condensation at heat exchanger level, it is strongly recommended to insulate
the water pipes.
The water-cooled cabinet is equipped with two 1”1/4 tapered connectors for connection to
the site cooling unit and one 20 mm nozzle for connection to the site drain.
It is necessary to prepare the cooling unit for connection to the water-cooled cabinet ahead
of the installation date, taking care to provide sufficient space for connection and
disconnection.
The following figure shows an example of plumbing installation for a water-cooled cabinet.
Figure 15. Water-cooled cabinet connection (example)
mportant You are advised to clearly label the inlet and outlet water hoses.
4.4.
Cooling Unit Fixtures for Water-Cooled Cabinets
You are responsible for providing all required water supply circuit fixtures, such as:
•
•
Armored hoses and connectors
Stainless steel filters (Diameter: 0.3 mm / Length: 3 cm min.)
Filters must be equipped with removable strainers and must be placed on the water inlet
by-pass circuits. These filters offer protection against foreign bodies and impurities.
Pressure gauges
Thermometers
Flow meters
...
•
•
•
•
4-4
- Site Preparation Guide