1.2.
Deliver y Conditions
The equipment is delivered 24 hours in advance of the scheduled installation date. On
arrival, the equipment must be placed, in its packing, in the Computer Room so that it
reaches room temperature before powering up (optimum operating temperature = 22
°
C +
3
°
C, hygrometry = 50% + 5%).
WARNING
To avoid incorrect handling, the equipment must be removed from its packing by authorized
Customer Service Engineers only.
1.3.
Carr y-In Route
The route from the unloading bay to the Computer Room must be checked to ensure that the
equipment can be carried into the premises easily and that floors can support temporary
overloads.
mportant
Access doors must be at least 2.10 meters high to allow rack-mounted
equipment to be transported vertically.
CAUTION
The equipment must be transported as indicated on packing labels.
The equipment may be extremely heavy and require the use of an elevator.
The Data Processing Site manager must allocate enough personnel to ensure safe handling of
the equipment.
Chapter 1.
Fitting out the Premises
1-3