30
5.5.3
Inspecting the water installation
Check the following topics:
– Water supply
Has filter valve (accessory “Z21”) or shut-off valve and µm water filter respectively been
installed in supply line?
Have admissible water pressure (1 – 10 bar) and admissible temperature (1 – 0 °C) been
observed?
Does the supply capacity match the steam generator and is the minimum inside diameter of
the supply pipe maintained throughout the entire length?
Are all components and pipes properly secured and are all threaded connections securely
tightened?
Is the water system properly sealed?
Does the water supply installation meet the requirements of the local regulations for water
installations?
– Water drain
Is the minimum inside diameter of the drain pipe of 0 mm maintained throughout the entire
length?
Has drain pipe been installed with a downslope of at least 10 %?
Has the heat resistance of the material used been verified to be at least 100 °C?
Is the drain hose properly secured (hose clamps at unit connection tightened)?
Does the water drain installation meet the requirements of the local regulations for water
installations?