3-18
l I n s t a l l a t i o n - Te s t i n g
Testing the Primar y Receiver
(optional)
1
Make sure there is no material in the drying hopper.
2
Disconnect the material inlet hose of the optional receiver(s) at the source.
3
Start the dryer.
Monitor the dryer during the first few minutes of operation to
verify that the start-up operating sequences are correct.
4
Login to the dryer’s control under the appropriate user name and pass-
word.
See Operation section entitled, Control Function Descriptions, Login
Screen.
5
Navigate to the System Overview Screen.
6
Press the receiver’s magnifying glass icon to access the Primary Loader
Screen.
(continued)
NOTE:
Refer to loader manual
for installation instructions.
✐
Содержание Carousel Plus UGD043-1216
Страница 7: ...Table of Contents l v...
Страница 8: ...vi l Table of Contents...
Страница 48: ...3 24 l Installation Testing...
Страница 54: ...4 6 l Operation Control Function Flow Charts continued Login Flow Chart...
Страница 55: ...4 O p e r a t i o n Operation l 4 7 Operation Basic Controls...
Страница 56: ...4 8 l Operation Control Function Flow Charts continued Operation Flow Chart 1 continued...
Страница 57: ...4 O p e r a t i o n Operation l 4 9 Control Function Flow Charts continued Operation Flow Chart 2 continued...
Страница 58: ...4 10 l Operation...
Страница 59: ...Operation Dew Point Package Controls 4 O p e r a t i o n Operation l 4 11...
Страница 60: ...Control Function Flow Charts continued Operation Flow Chart 1 4 12 l Operation...
Страница 61: ...Control Function Flow Charts continued Operation Flow Chart 2 4 O p e r a t i o n Operation l 4 13...
Страница 62: ...4 14 l Operation...
Страница 63: ...4 O p e r a t i o n Operation l 4 15 Operation Setup Control...
Страница 64: ...4 16 l Operation Control Function Flow Charts continued continued Setup Flow Chart 1...
Страница 66: ...4 18 l Operation continued Control Function Flow Charts continued Equipment Setup Flow Chart 2...
Страница 164: ...6 46 l Troubleshooting...