3.1.7 Snap cable retention assemblies into the appropriate locations. Secure with bolts if grounded.
See photos 3-5.
3.1.8 Store express buffer tube(s) as seen in photo 8. Store inline cable entering from right side first, then cable
entering from left side. Tray stack may be removed for easier access to storage. See photos 6-8.
3.1.9 Create mid-span opening of LBT containing fiber to be spliced as follows: mark buffer tube 5” from the sheath
opening on cable entering closure from the left. Mark buffer tube 10” from the sheath opening on the
cable entering closure from the right. Remove 41” of buffer tube between the two marks. See Figure 2.
3.1.10 Cut fibers to be spliced 41” from the buffer tube opening from incoming signal side of cable
3.1.11 Proceed to
section 3.4
Fiber Routing and Splicing.
Photo #7
Storage
Store express LBT
Photo #8
Squeeze
tab. Lift up
to remove
Squeeze
tab. Lift up
to remove
Photo #6
Photo #3
Left
side entry
port. No ground
Snap into
cavity
Photo #5
Left side & Right side entry
ports. Ground bar & Inline bar
Snap into cavity
& install (3) bolts.
Photo #4
Snap into
cavity
Right
side entry
port. No ground
Figure 2
Fiber to be
spliced 41”
Cable entering
closure from
LEFT
Cable entering
closure from
RIGHT
LBT 5”
LBT 10”
Mini
-
OTE 300 Installation Guide