FRAME ASSEMBLY (CONTINUED)
7. Repeat the steps for the remaining rafters and purlins
to complete the frame assembly.
IMPORTANT:
Refer to Quick Start Guide to properly
position the rafters with ratchets
.
When adding purlin pipe sections, secure each pipe
joint with a single Tek screw.
8. After each cross connector is tighten, secure the cross
connector to the rafter and the purlin pipe to the cross
connector as shown below.
9. After the frame is assembled and the final end rafter is
attached, return to and verify that each connection is
secure.
Do not allow the purlins to extend beyond the
outer edge of the end rafter.
NOTE:
The purlin positions shown above may vary
slightly from the actual purlin locations for your shelter.
10. With all rafters in place, wrap each connector with
two layers of duct tape to protect the cover when it is
installed.
11. Continue by squaring and anchoring the assembled
frame.
Install Tek