7
GATE
CONDUIT & CONCRETE PAD
Gate must be constructed and installed according to ASTM F2200
standards (refer to page 4). Gate must fit specifications of operator
(refer to specifications).
Trench and install conduit. Before trenching, contact underground
utility locating companies. Conduit must be UL approved for low and
high voltage. Consider the operator placement BEFORE installing the
pad or post.
Concrete Pads
SAFETY
Entrapment protection devices are required to protect against any
entrapment or safety conditions encountered in your gate application.
Install warning signs on both sides of the gate.
Warning Signs
Entrapment Danger
VEHICLE LOOPS
The vehicle loops allow the gate to stay open when vehicles are
obstructing the gate path. Suggested for vehicles 14 feet (4.27 m) or
longer. Vehicle loops are not required but are recommended.
(Inside Property)
SITE PREPARATION
Check the national and local building codes
BEFORE
installation.
INTRODUCTION
CHECK YOUR GATE
Gate MUST be level. Gate and gate
post MUST be plumb. Gate MUST
have smooth bottom edge, no
protrusions should exist.
Remove ANY/ALL wheels
from the bottom of gate.
Gate MUST NOT hit or drag
across the ground.
Gate MUSTswing freely and
be supported entirely by its
hinges.