44
APPENDIX
TOP VIEW OF OPERATOR AND GATE
Gate Open
90°
Gate Hinge Center
26-1/2"
9"
Output Shaft Center
Wall
28"
24"
Handle
STEP 2
CONCRETE PAD AND OPERATOR
ATTACHMENT
COMPACT INSTALLATION ONLY
Check the national and local building codes before installation.
1. Install the electrical conduit.
2. Pour a concrete pad (reinforced concrete is recommended). The
concrete pad should be 6 inches above the ground and deeper than
the frost line. Ensure the pad is tall enough to avoid possible flooding.
3. Secure the operator to the concrete pad with appropriate fasteners.
NOTE:
An alternative to a concrete pad is to post mount the operator
(refer to accessories).
4 Concrete
Anchors
1/2" x 3 1/2"
Below the frost
line. Check all
national and
local codes.
6" Above Ground
28"
1
3
Post Mount
24"
CONDUIT LOCATION
MOUNTING FOOTPRINT
5.5"
4.5"
1"
6.5"
4"
1.5"
10"
3"
28"
20"
15"
24"
13.6"
12.2"
6.1"
2.49"
14"
14.82"
(cover mounting distance)
(Conduit)
(Pad)
24"-32"
STEP 1
DETERMINE LOCATION FOR CONCRETE
PAD AND OPERATOR
COMPACT INSTALLATION ONLY
DO NOT run the operator until instructed.
Refer to the illustration to determine the measurements and location of
the concrete pad.
NOTE:
When lifting the operator use the handle to avoid damaging the
operator.
NOTE:
There should only be a maximum of 4" (10.2 cm)
from the center of the hinge to the edge of the post or
column. If the distance is greater than 4" (10.2 cm)
entrapment protection for this area is required.
4" (10.2 cm) maximum
2