Installation Guide for FibeAir IP-20C-HP
Page 202 of 204
Ceragon Proprietary and Confidential
9.3.2.4
Management Verification
•
Launch the HTTP management and verify that you can manage the link and that you are able
to perform changes to the link configuration (frequency channel, Tx power, system name,
time & date, etc.)
•
Verify that correct parameters are reported when performing the above.
•
Verify that there are no active alarms on the link.
•
If the management station is located at a remote site (Network Operation Center), verify
that the management station can manage the link and receive traps.
9.4
IP-20 Commissioning Log
The Commissioning Log is an integral part of the commissioning procedure and
should be filled in for each installed link.
The Commissioning Log gathers all relevant information regarding the installed
link and contains a checklist of all recommended commissioning tests.
Maintaining the Commissioning Log is important for tracking your installations,
and to provide essential data for Ceragon Networks.
Upon completing the Commissioning Log, send the log to Ceragon support center
at
IP-20 LINK COMMISSIONING LOG
1. GENERAL INFORMATION
Customer:
Radio model:
Configuration:
Radio link code:
Site 1 name & add:
Site 2 name & add:
2. ODU/RFU
Site 1
Site 2
ODU model:
ODU p/n:
ODU s/n:
ODU SW:
Tx frequency (MHz):
Rx frequency (MHz):
Link ID:
Tx power (dBm):